🔍 Case Overview:
In one more commercial case (Judgment No. 296/2020/KDTM-PT issued on May 13, 2020, by the Ho Chi Minh City People’s Court), a dispute arose between Company A (Investor) and Company C (General Contractor) regarding a construction contract for the A&B Saigon Tower project.
Company A terminated the contract, citing delays and substandard construction quality, and demanded:
✅ Refund of overpaid advances: 4.3 billion VND
✅ Penalties for delay: 10.8 billion VND
✅ Compensation for damage: 5.1 billion VND
💰 Total liability: 20.58 billion VND (~$860,000)
The Defendant (Company C) appealed, arguing:
– The contract was mutually terminated, as Company A had no construction permit at the time.
– The delays were not significant, and they had rectified all alleged quality issues.
– The penalties imposed were unjustified.
⚖ Legal Analysis & Court Ruling
The court upheld the original judgment, emphasizing key legal points:
📌 Breach of contract: The contractor failed to meet deadlines, exceeding the contractual limit of 42 days for delays.
📌 Quality defects: Expert reports confirmed non-compliance with design standards, requiring costly remedial work.
📌 Penalty enforcement: The agreed penalty clause (8% of the unfulfilled contract value) was enforceable under Vietnamese law.
📌 Evidence burden: The contractor failed to provide counter-evidence proving compliance or mitigating factors.
📢 Key Takeaways for Businesses
💡 1. Contract Clauses Matter – Ensure your contract includes clear deadlines, penalties, and termination conditions to avoid disputes.
💡 2. Documentation is Key – Always maintain detailed records of project progress, approvals, and issue resolutions to defend against claims.
💡 3. Legal Compliance First – Proceeding without a construction permit weakens the investor’s position and may lead to mutual liability risks.
💡 4. Effective Dispute Resolution – Early mediation or arbitration can prevent costly litigation and preserve business relationships.
📢 Final Thought
This case serves as a critical lesson for both investors and contractors in the construction industry. Contractual non-compliance and project mismanagement can lead to severe financial consequences.
What are your thoughts on contract enforcement in construction projects?
Link PDF: https://drive.google.com/file/d/14qxk7SYKdqm8Ms_Qb56b726ZMfqNWeyF/view?usp=sharing

Should you need any legal support, don’t hesitate to reach out to our Lawyers & Associates. We are pleased to assist your legal need.
THE LAM LAW LLC
🏢Indochina Park Tower, # 4 Nguyen Dinh Chieu Str, Dakao Ward, Dist 1, Ho Chi Minh City.
📞Tel: +84 (0)28 710 58 222 – 6288 3798 – Hotline: +84 (0) 97 309 77 77
✉ Email: info@thelamlawllc.com
Related Posts
Penalties vs. Late Payment Interest in Commercial Contracts
When clients or partners delay payments, what legal remedies can businesses rely on to both
Oct
Celebration events for Vietnam Lawyers’ Day & Vietnam Law Day
🌟 In celebration of Vietnam Lawyers’ Day and Vietnam Law Day, THE LAM LAW LLC
Oct
Recap GES HCMC Interview Round 2025
On Sunday, September 28, 2025, THE LAM LAW LLC – Your legal need, Our Mission
Oct
Draft Decree Guiding the Law on Personal Data Protection
As of today, Decree No. 13/2023/ND-CP remains the sole detailed regulation on personal data protection
Oct
Startup Career Talk at Ho Chi Minh City University of Law
Yesterday, September 23, 2025, THE LAM LAW LLC – Your legal need, Our Mission, represented
Sep
Legal Insight: Corporate Tax Handbook 2025
The Corporate Tax Handbook 2025 has just been released, marking significant updates to Vietnam’s tax
Sep