🔍 Case Overview:
In one more commercial case (Judgment No. 296/2020/KDTM-PT issued on May 13, 2020, by the Ho Chi Minh City People’s Court), a dispute arose between Company A (Investor) and Company C (General Contractor) regarding a construction contract for the A&B Saigon Tower project.
Company A terminated the contract, citing delays and substandard construction quality, and demanded:
✅ Refund of overpaid advances: 4.3 billion VND
✅ Penalties for delay: 10.8 billion VND
✅ Compensation for damage: 5.1 billion VND
💰 Total liability: 20.58 billion VND (~$860,000)
The Defendant (Company C) appealed, arguing:
– The contract was mutually terminated, as Company A had no construction permit at the time.
– The delays were not significant, and they had rectified all alleged quality issues.
– The penalties imposed were unjustified.
⚖ Legal Analysis & Court Ruling
The court upheld the original judgment, emphasizing key legal points:
📌 Breach of contract: The contractor failed to meet deadlines, exceeding the contractual limit of 42 days for delays.
📌 Quality defects: Expert reports confirmed non-compliance with design standards, requiring costly remedial work.
📌 Penalty enforcement: The agreed penalty clause (8% of the unfulfilled contract value) was enforceable under Vietnamese law.
📌 Evidence burden: The contractor failed to provide counter-evidence proving compliance or mitigating factors.
📢 Key Takeaways for Businesses
💡 1. Contract Clauses Matter – Ensure your contract includes clear deadlines, penalties, and termination conditions to avoid disputes.
💡 2. Documentation is Key – Always maintain detailed records of project progress, approvals, and issue resolutions to defend against claims.
💡 3. Legal Compliance First – Proceeding without a construction permit weakens the investor’s position and may lead to mutual liability risks.
💡 4. Effective Dispute Resolution – Early mediation or arbitration can prevent costly litigation and preserve business relationships.
📢 Final Thought
This case serves as a critical lesson for both investors and contractors in the construction industry. Contractual non-compliance and project mismanagement can lead to severe financial consequences.
What are your thoughts on contract enforcement in construction projects?
Link PDF: https://drive.google.com/file/d/14qxk7SYKdqm8Ms_Qb56b726ZMfqNWeyF/view?usp=sharing
Should you need any legal support, don’t hesitate to reach out to our Lawyers & Associates. We are pleased to assist your legal need.
THE LAM LAW LLC
🏢Indochina Park Tower, # 4 Nguyen Dinh Chieu Str, Dakao Ward, Dist 1, Ho Chi Minh City.
📞Tel: +84 (0)28 710 58 222 – 6288 3798 – Hotline: +84 (0) 97 309 77 77
✉ Email: info@thelamlawllc.com

Tiếng Việt
Related Posts
Happy Women’s Day!
On the occasion of International Women’s Day, THE LAM LAW LLC would like to extend
Mar
Mitigating supply chain risks amid Middle East conflicts
The geopolitical situation in the Middle East has escalated sharply, directly impacting international trade for
Mar
When is property acquired before marriage considered common asset?
Does being the sole name on a Land Use Right Certificate before official marriage automatically
Feb
Precedent No. 78/2025/AL
“EQUITY” OR “BUSINESS FUNDING” – NAVIGATING THE LEGAL SUBSTANCE As we embrace the Year of
Feb
Happy Lunar New Year 2026
🌸🧧 Dear Customers and Partners, Spring has arrived, bringing with it bright new beginnings and
Feb
Year End Party 2025
✨ CLOSING A MEMORABLE YEAR – OPENING A NEW JOURNEY 📅 On February 7, 2026,
Feb