On 08 May 2026, the Ministry of Construction issued Official Letter No. 6761/BXD-KTQLXD regarding the adjustment of construction contracts in the context of significant fluctuations in fuel and construction material prices.
This guidance carries substantial practical implications for:
🏗 Project owners
🏗 Contractors
🏗 EPC projects
🏗 Infrastructure and public investment developments in Vietnam
🔍 Key Legal Highlights
📌 Recognition of “Force Majeure” & “Fundamental Change of Circumstances”
The Ministry reaffirmed the legal basis under:
– The 2015 Civil Code
– The amended Law on Construction 2025 (effective from 01 July 2026)
Accordingly, severe fluctuations in fuel and construction material prices may be considered:
✔ Force majeure events; or
✔ Fundamental changes of circumstances affecting contract performance.
👉 This creates an important legal foundation for:
– Contract renegotiation
– Price adjustment requests
– Risk-sharing mechanisms between parties
📌 Lump-Sum & Fixed-Price Contracts May Still Be Adjusted
One of the most notable points is the confirmation that:
⚠️ Even lump-sum and fixed-price construction contracts may be adjusted where:
– Force majeure occurs; or
– Circumstances fundamentally change during contract performance.
👉 This is particularly significant for:
✔EPC contracts
✔Infrastructure projects
✔Large-scale public investment works
📌 Strong Emphasis on Contract Risk Management
The Ministry encourages parties to:
✔ Assess the actual impact of market fluctuations
✔ Review contract timing and completed workloads
✔ Carefully evaluate adjustment mechanisms, price indices, and supporting data
👉 The guidance reflects a growing legal and practical trend toward:
⚖️ Fair risk allocation and flexible contract management rather than rigid enforcement under extraordinary market conditions.
📌 Potential Impact on Construction Disputes & Claims
In practice, significant price volatility often leads to:
❗ Delays in project execution
❗ Claims for price adjustment
❗ Extension of time requests
❗ Construction disputes and arbitration proceedings
👉 Businesses should therefore pay close attention to:
✔Price adjustment clauses
✔Force majeure provisions
✔Claims management procedures
✔Evidence and cost fluctuation documentation
🎯 Practical Perspective
As Vietnam continues accelerating major:
🏗 Infrastructure
🏗 Energy
🏗 Public investment projects
…the importance of adaptive contract structures and effective risk management mechanisms will continue to increase.
At TheLamLaw, we continue monitoring legal developments relating to:
⚖️ Construction contracts
⚖️ Infrastructure disputes
⚖️ Project risk management
⚖️ Arbitration & dispute resolution
📖 Source: Official Letter No. 6761/BXD-KTQLXD.
THE LAM LAW LLC
🏢Indochina Park Tower, # 4 Nguyen Dinh Chieu Str, Tan Dinh Ward, Ho Chi Minh City.
📞Tel: +84 (0)28 710 58 222 – 6288 3798 – Hotline: +84 (0) 973 097 777
✉ Email: info@thelamlawllc.com

Tiếng Việt
Related Posts
From Gratitude To Global Connections: A Meaningful Visit To Ulaw
🎓 𝗚𝗿𝗲𝗮𝘁 𝗽𝗮𝗿𝘁𝗻𝗲𝗿𝘀𝗵𝗶𝗽𝘀 𝗯𝗲𝗴𝗶𝗻 𝘄𝗶𝘁𝗵 𝗮 𝗺𝗲𝗮𝗻𝗶𝗻𝗴𝗳𝘂𝗹 𝗰𝗼𝗻𝘃𝗲𝗿𝘀𝗮𝘁𝗶𝗼𝗻.On the occasion of Vietnamese Teachers’ Day, a
Nov
Holiday Notice Vietnamese Culture Day
Dear Valued Clients and Partners, ⚖️ THE LAM would like to respectfully announce our holiday
Nov
Celebrating Vietnamese Teachers’ Day
On the occasion of Vietnamese Teachers’ Day (November 20), THE LAM would like to express
Nov
The 41st International Residency & Overseas Investment Information Exchange Forum 2026
Behind every cross-border investment decision lies a bigger ambition—growing a business, finding a new home,
Nov
THE LAM congratulates the 19 new members of GES 26 HCMC
THE LAM LAW – Your legal need, Our Mission warmly congratulates the 19 new members
Nov
THE LAM joins hands in response to Vietnam Law Day
On the morning of November 8, 2026, THE LAM LAW LLC participated in the Walking
Nov