On 08 May 2026, the Ministry of Construction issued Official Letter No. 6761/BXD-KTQLXD regarding the adjustment of construction contracts in the context of significant fluctuations in fuel and construction material prices.
This guidance carries substantial practical implications for:
🏗 Project owners
🏗 Contractors
🏗 EPC projects
🏗 Infrastructure and public investment developments in Vietnam
🔍 Key Legal Highlights
📌 Recognition of “Force Majeure” & “Fundamental Change of Circumstances”
The Ministry reaffirmed the legal basis under:
– The 2015 Civil Code
– The amended Law on Construction 2025 (effective from 01 July 2026)
Accordingly, severe fluctuations in fuel and construction material prices may be considered:
✔ Force majeure events; or
✔ Fundamental changes of circumstances affecting contract performance.
👉 This creates an important legal foundation for:
– Contract renegotiation
– Price adjustment requests
– Risk-sharing mechanisms between parties
📌 Lump-Sum & Fixed-Price Contracts May Still Be Adjusted
One of the most notable points is the confirmation that:
⚠️ Even lump-sum and fixed-price construction contracts may be adjusted where:
– Force majeure occurs; or
– Circumstances fundamentally change during contract performance.
👉 This is particularly significant for:
✔EPC contracts
✔Infrastructure projects
✔Large-scale public investment works
📌 Strong Emphasis on Contract Risk Management
The Ministry encourages parties to:
✔ Assess the actual impact of market fluctuations
✔ Review contract timing and completed workloads
✔ Carefully evaluate adjustment mechanisms, price indices, and supporting data
👉 The guidance reflects a growing legal and practical trend toward:
⚖️ Fair risk allocation and flexible contract management rather than rigid enforcement under extraordinary market conditions.
📌 Potential Impact on Construction Disputes & Claims
In practice, significant price volatility often leads to:
❗ Delays in project execution
❗ Claims for price adjustment
❗ Extension of time requests
❗ Construction disputes and arbitration proceedings
👉 Businesses should therefore pay close attention to:
✔Price adjustment clauses
✔Force majeure provisions
✔Claims management procedures
✔Evidence and cost fluctuation documentation
🎯 Practical Perspective
As Vietnam continues accelerating major:
🏗 Infrastructure
🏗 Energy
🏗 Public investment projects
…the importance of adaptive contract structures and effective risk management mechanisms will continue to increase.
At TheLamLaw, we continue monitoring legal developments relating to:
⚖️ Construction contracts
⚖️ Infrastructure disputes
⚖️ Project risk management
⚖️ Arbitration & dispute resolution
📖 Source: Official Letter No. 6761/BXD-KTQLXD.
THE LAM LAW LLC
🏢Indochina Park Tower, # 4 Nguyen Dinh Chieu Str, Tan Dinh Ward, Ho Chi Minh City.
📞Tel: +84 (0)28 710 58 222 – 6288 3798 – Hotline: +84 (0) 973 097 777
✉ Email: info@thelamlawllc.com

Tiếng Việt
Related Posts
THE LAM LAW Joined the “Bringing Law and Compassion to the Border Areas of Tay Ninh” Journey (30–31 May 2026)
From 30–31 May 2026, THE LAM LAW – Your legal need, Our Mission was honored
Jun
THE LAM LAW LLC Recognized as “Best International Arbitration Law Firm – HCMC 2026”
THE LAM LAW – Your legal need, Our Mission is honored to be recognized by
May
“Subrogation Right” in Maritime Cargo Claims
When an insurer pays compensation to the cargo owner after a maritime loss, can the
May
Vietnam’s Foreign Investment Outlook 2026
THE LAM LAW – Your legal need, Our Mission is honoured to reshare that our
May
Vietnam Economic Update – May 2026
THE LAM LAW – Your legal need, Our Mission is pleased to share a visual
May
Vietnam officially establishes a legal framework for Electronic Labor Contracts
It’s last Friday, Vietnam’s Ministry of Home Affairs has officially issued Circular No. 08/2026/TT-BNV guiding
May