⚖️ SUPREME COURT OVERTURNS CONSTRUCTION DISPUTE RULING – A CASE STUDY IN PENALTY & DEBT OFFSET PROCEDURE
🔍 CASE SUMMARY
In Decision No. 15/2016/KDTM-GĐT, the Supreme People’s Court of Vietnam reviewed a construction dispute between Company A (Vietnam) and Company B (China) over a subcontract for MEP works worth USD 5.1 million. The dispute arose from:
🔹 Additional works increasing the contract value by ~USD 600,000.
🔹Company A completed the project and obtained final acceptance.
🔹However, Company B only paid USD 5.2 million, leaving USD 549,978 unpaid.
🔹Company B claimed it had offset penalties for delays and quality issues, totaling USD 357,988, and recognized only USD 133,000 in remaining warranty-related debt.
Lower courts rejected Company A’s claim for the full amount, concluding that the penalty offsets were valid.
🧑⚖️ THE SUPREME COURT’S VIEWS
✅ On Liquidated Damages (5% Delay Penalty):
🔸 The Supreme Court found that the lower courts failed to verify whether the penalties were properly imposed according to contract terms, including:
– Timely notification of delay,
– Decisions by the Project Manager in accordance with Clause 3.5, and
– Presence of a valid claim or payment certificate.
🔸 Evidence showed Company A only accepted part of the penalty, not the full 5%.
✅ On Debt Offset Procedure:
🔸The court emphasized that offsetting debts requires:
– Mutual acknowledgment of amounts owed,
– Adherence to contractual procedures, and
– Transparent account reconciliation.
🔸No clear proof was presented that offsetting was agreed before or after reconciliation.
✅ On Judicial Oversight:
🔸The Supreme Court invoked Articles 337, 343, and 345 of the Civil Procedure Code (2015) to annul the judgments and return the case for retrial by the Hanoi People’s Court.
📌 KEY LEGAL LESSONS
✅ For Subcontractors:
Never assume silence means agreement. Always demand formal documentation for penalties and ensure timely dispute resolution clauses are followed.
✅ For Contractors & Employers:
Even with clear contract clauses, procedural compliance is critical when applying penalties or offsets. Unilateral deductions without due process are risky.
✅ For Legal Practitioners & Courts:
Do not treat internal reports or payment logs as definitive. Due diligence in contractual enforcement and dispute procedures is fundamental, especially in FIDIC construction contracts.

THE LAM LAW LLC
🏢Indochina Park Tower, # 4 Nguyen Dinh Chieu Str, Dakao Ward, Dist 1, Ho Chi Minh City.
📞Tel: +84 (0)28 710 58 222 – 6288 3798 – Hotline: +84 (0) 97 309 77 77
✉ Email: info@thelamlawllc.com
Related Posts
Announcement of holiday schedule 30/4 – 01/5/2025
THE LAM LAW LLC would like to inform all valued customers and partners about the
Apr
Professional exchange – Exploring cross-border collaboration
This afternoon at THE LAM LAW LLC – Your legal need, Our Mission office, Founder
Apr
Office Closure for Hung Kings’ Festival 2025
Dear Valued Customers and Partners, On the occasion of the Hung Kings’ Commemorations, we
Apr
What Does a “Lump-sum Contract” Really Mean?
🤔 What Does a “Lump-sum Contract” Really Mean? Lessons from a Complex Project Management & Design
Mar
Discussion Session with GES Ho Chi Minh 2024
✨ On March 13, 2025, THE LAM LAW LLC had the pleasure of hosting members of
Mar
Commercial Dispute – Late Payment Interest in Construction Contracts: Trade Law or Construction Law?
📌Commercial Dispute – Late Payment Interest in Construction Contracts: Trade Law or Construction Law?
Mar