🔍 Case Overview:
In one more commercial case (Judgment No. 296/2020/KDTM-PT issued on May 13, 2020, by the Ho Chi Minh City People’s Court), a dispute arose between Company A (Investor) and Company C (General Contractor) regarding a construction contract for the A&B Saigon Tower project.
Company A terminated the contract, citing delays and substandard construction quality, and demanded:
✅ Refund of overpaid advances: 4.3 billion VND
✅ Penalties for delay: 10.8 billion VND
✅ Compensation for damage: 5.1 billion VND
💰 Total liability: 20.58 billion VND (~$860,000)
The Defendant (Company C) appealed, arguing:
– The contract was mutually terminated, as Company A had no construction permit at the time.
– The delays were not significant, and they had rectified all alleged quality issues.
– The penalties imposed were unjustified.
⚖ Legal Analysis & Court Ruling
The court upheld the original judgment, emphasizing key legal points:
📌 Breach of contract: The contractor failed to meet deadlines, exceeding the contractual limit of 42 days for delays.
📌 Quality defects: Expert reports confirmed non-compliance with design standards, requiring costly remedial work.
📌 Penalty enforcement: The agreed penalty clause (8% of the unfulfilled contract value) was enforceable under Vietnamese law.
📌 Evidence burden: The contractor failed to provide counter-evidence proving compliance or mitigating factors.
📢 Key Takeaways for Businesses
💡 1. Contract Clauses Matter – Ensure your contract includes clear deadlines, penalties, and termination conditions to avoid disputes.
💡 2. Documentation is Key – Always maintain detailed records of project progress, approvals, and issue resolutions to defend against claims.
💡 3. Legal Compliance First – Proceeding without a construction permit weakens the investor’s position and may lead to mutual liability risks.
💡 4. Effective Dispute Resolution – Early mediation or arbitration can prevent costly litigation and preserve business relationships.
📢 Final Thought
This case serves as a critical lesson for both investors and contractors in the construction industry. Contractual non-compliance and project mismanagement can lead to severe financial consequences.
What are your thoughts on contract enforcement in construction projects?
Link PDF: https://drive.google.com/file/d/14qxk7SYKdqm8Ms_Qb56b726ZMfqNWeyF/view?usp=sharing
Should you need any legal support, don’t hesitate to reach out to our Lawyers & Associates. We are pleased to assist your legal need.
THE LAM LAW LLC
🏢Indochina Park Tower, # 4 Nguyen Dinh Chieu Str, Dakao Ward, Dist 1, Ho Chi Minh City.
📞Tel: +84 (0)28 710 58 222 – 6288 3798 – Hotline: +84 (0) 97 309 77 77
✉ Email: info@thelamlawllc.com

Tiếng Việt
Related Posts
THE LAM LAW – Notable Firm in the Asialaw 2026 Rankings.
🏆 A milestone for our firm. A shared achievement with those who trust us.THE LAM
Oct
Happy Vietnamese Women’s Day
On the occasion of Vietnamese Women’s Day, THE LAM wishes all women, female Lawyer &
Oct
Happy Vietnamese Lawyer’s Traditional Day
💖 Warmest congratulations on the 81th Anniversary of Vietnam Lawyers’ Traditional Day (October 10, 1945
Oct
Supporting the Next Generation of Legal Professionals – VMOOT 2026
THE LAM LAW – Your legal need, Our Mission was honoured to support VMoot2026, the
Oct
THE LAM joins V-MED 2026
On 26–27 September 2026, the Final Round of the Vietnam Mediation Moot (V-MED 2026) was
Sep
Strengthening Connections, Building Trust & Creating Business Opportunities
Yesterday morning, September 22, 2026, THE LAM LAW – Your legal need, Our Mission was
Sep